Read ZADCO Future Projects-Tenders to the Market EPC-MPC-SUFEMS (05 02 2010).xlsx text version

Type

Name of the Project/Tender

Brief Scope of Work

Location of the Project

Planned start & finish Dates

1

Construction

P-8363 : Fire & Gas detection system at Zirku

ZADCO have carried out a QRA in order to assess and evaluate the effects of loss of containment on its Oil & Gas facilities on Zirku Island. From the findings of this study there was a recommendation to provide adequate F&G detection and alarm system to replace the existing aging system. As a result, ZADCO has initiated this project with the aim of providing Zirku with a new F&G system to increase the level of safety on the facility. EPC works to be carried out. Upgrade Zirku airport to handle additional traffic due to Fixed Wing aircrafts flights and helicopters. P-8276: Gas Injection and Gas Lift Facilities

Zirku

Planned Award : Q1 2012 Finish : Q3 2013

2

Construction

P 8381 - Zirku Airport Upgrade

Zirku

Planned Award : Q3 2011 Finish : Q4 2012 Planned Award : Q1 2011 Finish : Q1 2012 Planned Award : Q1 2011 Finish : Q1 2012 Planned Award : Q2 2011 Finish : Q1 2013 Planned Award : Q3 2012 Finish : Q1 2015 Planned Award : Q3 2012 Finish : Q1 2015 Planned Award : Q3 2012 Finish : Q3 2015 Planned Award : Q3 2012 Finish : Q4 2016 Planned Award : Q1 2010 Finish : Q4 2011

3

Construction

UZ750 Brownfiled Projects

Upper Zakum

4

Construction

UZ750 Brownfiled Projects

P-8316 Slot Extension Works

Upper Zakum

5

EPC

P-8383 - UZ 750 Surface Facilities

Early Production System - First Oil Early Production System - Greenfield Facilities & Satellite/Central Platform Brwon Field Early Production System - Subsea Pipelines & Cables

Upper Zakum

6

EPC

P-8383 - UZ 750 Surface Facilities

Upper Zakum

7

EPC

P-8383 - UZ 750 Surface Facilities

Upper Zakum

8

EPC

P-8383 - UZ 750 Surface Facilities

Production Build Up - Greenfield Facilities

Upper Zakum

9

EPC

P-8383 - UZ 750 Surface Facilities

Non Process Civil Works & Accommodation

Upper Zakum

10

EPC

P - 8163 Procurement & Installtion of 3rd Power Procurement and installtion of 3.3 MW Power Generation Unit at Generation Ubit UAD CPC

UAD

11

EPC

P - 8863 Upgrading of existing Power Generation The existing two Gas Turbine power generation Units to be Units at UAD CPC upgraded to higher capacity to meet growing power demand.

UAD

Planned Award : Q4 2010 Finish : Q4 2011

12

EPC

P - 7335 Procurement & Installtion of 2MW Diesel To provide reliable power supply a 2MW Diesel Generator Set to Generator Set be procured and installed at Arzanah Island

Satah

Planned Award : Q4 2010 Finish : Q2 2013

13

FEED

P-8383 - UZ 750 Surface Facilities

FEED for Pprduction Build Up

Upper Zakum

Planned Award : Q4 2010 Finish : Q3 2011

Type

Name of the Project/Tender

Brief Scope of Work

Location of the Project

Planned start & finish Dates

14

FEED & EPC

Installation of two RO type desalination plants, each with capacity P-8362 :Potable Water & Sewage Treatment Plant of 1200m3/day to meet acute shortage of potable water and at Zirku sewage treatment plant at Zirku. FEED & EPC works to be carried for this project.

Zirku

FEED Planned Award : Q3 2010 Finish : Q1 2012 EPC Planned Award : Q4 2012 Finish : Q4 2014 FEED Planned Award : Q1 2011 Finish : Q1 2012 EPC Planned Award : Q1 2014 Finish : Q4 2015 FEED Planned Award : Q4 2010 Finish : Q4 2011 EPC Planned Award : Q4 2012 Finish : Q2 2014 FEED Planned Award : Q1 2012 Finish : Q4 2012 EPC Planned Award : Q1 2014 Finish : Q3 2016 FEED Planned Award : Q1 2011 Finish : Q4 2011 EPC Planned Award : Q3 2012 Finish : Q4 2014 EPC Planned Award : Q3 2010 Finish : Q1 2012

15

FEED & EPC

UZ750 Brownfiled Projects

P-8385 Switchgear Replacement

Upper Zakum

16

FEED & EPC

UZ750 Brownfiled Projects

P-8341 Water Injection Plant Upgrade & P-8361 Cooling Water System Upgrade

Upper Zakum

17

FEED & EPC

P - 7224 UAD Full Field Field Development

Full field development based on installtion of ESPs. The project will include installtion of new platform for equipment, replacement of infield pipe lines and installtion of surface facilities.

UAD

18

Project

P 8374 - Power upgrade at ZIRKU

Installation of additional power generation facilities at Zirku Island since the existing power generation facilities enhancement due to the operational constraints for maintenance of aging turbines, increase in demand for the future projects and improve flexibility of operations

Zirku

19

Project

Package 1 : Replace the existing pipeline for Oily Water with more P 8424 - Oily Water Treatment and Disposal at reliable and durable flexible pipeline system along with associated ZIRKU components. EPC works

Zirku

Information

ZADCO Future Projects-Tenders to the Market EPC-MPC-SUFEMS (05 02 2010).xlsx

2 pages

Find more like this

Report File (DMCA)

Our content is added by our users. We aim to remove reported files within 1 working day. Please use this link to notify us:

Report this file as copyright or inappropriate

516342


You might also be interested in

BETA
ZADCO Future Projects-Tenders to the Market EPC-MPC-SUFEMS (05 02 2010).xlsx